Fulian Kalan, Narwana (Jind), Haryana: In a decisive humanitarian and developmental intervention, a persistent 10-to-12-year wastewater crisis in Fulian Kalan village, Narwana Tehsil, Jind District, Haryana, has been permanently addressed under the direction of Sant Rampal Ji Maharaj. Responding directly to an appeal made by the village Gram Panchayat, He ordered an immediate technical survey and sanctioned the delivery of a 3600-foot-long, 8-inch-diameter pipeline, a 10 HP electric motor, and all essential pipeline fittings within 24 hours. This comprehensive relief effort has averted structural damage and health hazards for approximately 200 to 250 households that routinely suffered from dirty water overflow.
- How Villagers Approached Sant Rampal Ji Maharaj for Help: The 12-Year Plight
- Rapid Technical Survey and Sanction Within 24 Hours
- Detailed Summary of Sanctioned Equipment and Materials
- Operational Guidelines and Technical Execution
- Eyewitness Accounts and Community Testimonials
- Praise to the Divine Grace and Benevolence of Sant Rampal Ji Maharaj
How Villagers Approached Sant Rampal Ji Maharaj for Help: The 12-Year Plight
For more than a decade, Fulian Kalan lacked an effective drainage mechanism for its central wastewater pond. The dirty water of the entire village accumulated in this pond, which had no outlet. During rainy seasons, the pond routinely overflowed into residential streets and flooded residential structures.
The village Sarpanch representative, Maidan Singh (father-in-law of the sitting Sarpanch Kavita), explained that the Gram Panchayat owned no adjacent land where wastewater could be naturally diverted. For 10 to 12 years, residents and representatives approached various administrative offices and government authorities, but no viable solution was provided.
The prolonged waterlogging caused severe degradation of village life. Wastewater entered between 100 and 150 homes directly, while threatening the foundations of 200 to 250 houses with potential collapse. Streets remained submerged under toxic, stagnant water, making basic movement difficult for school children, women, and dairy cattle. The stagnant water emitted noxious gases, created foul odors, and became a breeding ground for mosquitoes and vector-borne diseases.
Having exhausted all administrative avenues, a five-member village delegation traveled to seek the benevolence of Sant Rampal Ji Maharaj, having learned of His extensive charitable initiatives across Haryana. They submitted their collective prayer at His lotus feet, requesting pipeline infrastructure to channel the dirty water out to distant agricultural drains.
Rapid Technical Survey and Sanction Within 24 Hours
The response from Sant Rampal Ji Maharaj was immediate. Upon receiving the petition in the afternoon, He issued orders for a technical survey team to inspect Fulian Kalan. Remarkably, by the time the village delegation returned to Narwana from His ashram, the survey team was already on-site in the village.
The survey team utilized drone aerial surveillance and Google Maps satellite mapping to design a viable drainage route from the pond to the outer agricultural fields:
- Starting Point: The central contaminated village pond.
- Route Corridor: Extending along the main village thoroughfare toward the local grain market (Anaj Mandi).
- Intermediate Alignment: Passing the Scheduled Caste cremation ground road.
- Termination Point: Reaching the permanent concrete irrigation channel (Pakka Khal) leading into the fields.
- Total Measured Length: Exactly 1.1 kilometers (approximately 3,600 linear feet).
The technical survey report was submitted directly to Sant Rampal Ji Maharaj, who immediately granted full approval under Phase 2 of the Kisan Mazdoor Bachao Abhiyan (Save Farmer and Laborer Mission) and directed that all required materials be dispatched without delay.
Detailed Summary of Sanctioned Equipment and Materials
All hardware, piping, and mechanical assets needed to complete the underground drainage project were delivered directly to the Gram Panchayat:
| S. No. | Item / Material Description | Quantity / Specification | Operational Function in Project |
|---|---|---|---|
| 1 | Heavy-Duty PVC Pipeline | 3,600 Feet (8-Inch Diameter) | Underground transmission line spanning 1.1 km to the concrete drain |
| 2 | Heavy-Duty Electric Motor | 10 HP (Horsepower) | Pumping mechanism to lift wastewater from the pond into the pipeline |
| 3 | Kinetic Air Release Valves | Standard Technical Grade | Prevention of airlocks and negative pressure inside the pipeline |
| 4 | Pipe Bends and Joint Plates | Complete Required Set | Navigating roadway turns and ensuring structural pipe stability |
| 5 | PVC Adhesive / Solvent Cement | Industrial Grade | Hermetic sealing and leak-proofing of pipe joints |
| 6 | Flange Nuts, Bolts, and Hardware | Complete Technical Set | Mechanical securing of motor mountings and joint fittings |
Operational Guidelines and Technical Execution
During the official handover of materials to the Gram Panchayat, specific technical directives established by Sant Rampal Ji Maharaj were communicated to the local leadership:
- Underground Trenching: The Gram Panchayat undertook the responsibility of digging trenches and laying the 3600 feet of 8-inch pipes underground within one week.
- Hydraulic Leak Testing: Before backfilling the trenches with soil, the pipeline must be charged with water and air valves installed to verify that all joint connections are entirely watertight.
- Post-Installation Inspection & Motor Delivery: Following the underground installation, the survey team will conduct a verification inspection under His orders. Once verified, the 10 HP motor will be commissioned on-site to commence active pumping.
Eyewitness Accounts and Community Testimonials
- Maidan Singh, Sarpanch Representative:“For over ten years, contaminated water entered 100 to 150 homes in our village. We pleaded with government authorities repeatedly without success. We met Sant Rampal Ji Maharaj in the afternoon, and before we even reached back to our village, His survey team was already standing here. Within 24 hours, 3600 feet of pipes and all accessories arrived. We revere Sant Rampal Ji Maharaj as the very form of God.”
- Local Village Resident:“Our village was living in hellish conditions. Children were falling sick, roads were blocked, and the stench was unbearable. Sant Rampal Ji Maharaj initiated action within eight hours and saved more than 200 homes from destruction. No government or institution operates with such speed and compassion.”
Praise to the Divine Grace and Benevolence of Sant Rampal Ji Maharaj
The arrival of the relief convoy in Fulian Kalan turned the atmosphere of despair into one of immense celebration. Villagers gathered outside the Government Senior Secondary School to welcome the aid with devotional recitations (Mangalacharan), floral garlands, and slogans celebrating Sant Rampal Ji Maharaj.
Community members noted that where institutional mechanisms failed for over a decade, the profound compassion and boundless mercy of Sant Rampal Ji Maharaj brought an immediate and permanent resolution. Through His broader initiatives-including Phase 2 of the Kisan Mazdoor Bachao Abhiyan, the Pure Drinking Water Supply Campaign, and Livestock Protection Initiatives, He has extended life-saving drainage and drinking water infrastructure to over 100 crisis-hit villages, saving tens of thousands of acres of farmlands during floods and rescuing impoverished families. The residents of Fulian Kalan expressed their deepest adoration and eternal reverence for Sant Rampal Ji Maharaj, hailing Him as the true savior of the poor, farmers, and laborers.