For a farmer, his field is not merely a piece of land. It is his hard work, his hope, his family’s livelihood, and the foundation of his future. When this same field remains submerged in rainwater for a long time, it is not only the crop that is affected, but the farmer’s entire financial condition is also impacted.
- A Strong Beginning Towards Solving the Problem
- Steps Towards a Detailed and Permanent Solution
- Two 10 HP Motors and Technical Equipment Provided
- Assistance Provided Under Flood Relief Phase 2
- Detailed Account of the Total Assistance Provided
- Response and Experience of the Villagers
- The Special Feature of a Step-by-Step Solution
- New Hope and a Secure Future for Farmers
- A Permanent Solution Through the Grace of Sant Rampal Ji Maharaj
The same serious problem had existed for years in Girawad village of Jhajjar district, Haryana. Due to the lack of a proper system for draining rainwater, waterlogging occurred in the fields. This damaged crops and caused heavy losses to farmers.
To find a permanent solution to this serious problem, the village Gram Panchayat took a collective decision and presented a prayer at the feet of Sant Rampal Ji Maharaj. This prayer was not only for assistance. It carried a deep hope for a permanent solution to the village’s long-standing problem.
After this, the assistance that was received slowly began to change the condition of the village.
A Strong Beginning Towards Solving the Problem
Assistance was first provided to Girawad village under the Kisan Mazdoor Bachao Abhiyan.
In the first phase, the village was provided with 13,000 feet of 8-inch pipeline and three water drainage motors. The main objective of this assistance was to begin draining water from the major waterlogged areas of the village.
The villagers laid this pipeline underground according to the planned design. This work was completed through a collective effort in which the Gram Panchayat, farmers, and local people all participated.
After the success of the first phase, an improvement in the village’s water drainage situation became visible. However, some distant and newly affected areas still had a problem of accumulated water.
Steps Towards a Detailed and Permanent Solution
After the first phase, the Gram Panchayat again submitted a prayer before Sant Rampal Ji Maharaj.
This time, the scope of the problem was clearer because some additional fields were still affected by waterlogging. Considering this situation, the solution process was taken forward under Phase 2.
In the second phase, the village was provided with 28,000 feet of additional 8-inch pipeline.
This pipeline was provided to make the existing water drainage system stronger, wider, and more effective. The villagers also laid this pipeline underground according to the complete plan.
After the work was completed, the survey team conducted another inspection. During this inspection, a total of four water drainage lines were found to be completely correct according to the required standards. Based on this report, approval was given for further assistance.
Two 10 HP Motors and Technical Equipment Provided
After the survey report, on the orders of Sant Rampal Ji Maharaj, two additional motors were provided to the village. These motors were 10 HP Crompton company high-capacity motors, suitable for water drainage on a large scale.
Along with these motors, not only the machines but also a complete technical and branded setup was provided so that the entire system could operate smoothly without any obstruction. The major materials included were as follows:
Assistance Provided Under Flood Relief Phase 2
| Serial Number | Material | Details |
| 1 | Pipeline, First Phase | 13,000 feet, 8-inch |
| 2 | Pipeline, Second Phase | 28,000 feet, 8-inch |
| 3 | Total Pipeline | 41,000 feet |
| 4 | Additional Motors | 2 Crompton Motors, 10 HP |
| 5 | Starters | L&T company starters |
| 6 | Suction Pipes | 20 feet each |
| 7 | Cable Wire | Required quantity |
| 8 | PVC Pipes, Air Valves, Reducers | Complete material |
| 9 | Iron Bands, Clips, Steel Nuts and Bolts | Complete fitting set |
This complete arrangement ensures that the water drainage system continues to operate in a stable and effective manner for a long time.
Detailed Account of the Total Assistance Provided
Combining both phases, the assistance received by Girawad village so far is significant and extensive:
- Total Pipeline: 41,000 feet, 8-inch
- Total Motors: 5, including both phases
- Technical Fitting Material: Complete branded and industrial-level setup
- Water Drainage Lines: 4 main lines successfully installed and approved
This entire arrangement is being considered a major and decisive step toward permanently solving the village’s waterlogging problem.
Response and Experience of the Villagers
The village Sarpanch and villagers say that there is a clear difference between the situation before and now. Earlier, water remained accumulated in the fields for a long time. Now, with the water drainage system in place, the situation is continuously improving.
According to the villagers, if this entire system becomes fully active and operates smoothly, the problem of crop damage will be greatly reduced in the coming time. This can make farming safer, more stable, and more beneficial.
The Special Feature of a Step-by-Step Solution
The entire project in Girawad village is an example of how a major problem can be solved through a systematic, planned, and step-by-step process.
First, the pipeline was provided according to the requirement. It was then laid underground. After that, a survey was conducted. Finally, motors and technical materials were provided according to the requirement.
This entire process shows that merely providing assistance is not enough. A permanent solution is possible only through proper planning, monitoring, and systematic implementation.
New Hope and a Secure Future for Farmers
For the farmers of Girawad village, this project is not merely a technical arrangement. It is the foundation of new hope and a secure future. They now believe that rainwater accumulated in their fields will be able to drain out on time. This will help protect their crops and reduce losses.
The assistance provided by Sant Rampal Ji Maharaj under Annpurna Muhim is considered an important step toward stability, security, and self-reliance in the lives of farmers. This arrangement of 41,000 feet of pipeline and five motors is becoming a major change in strengthening the agricultural future of the village.
A Permanent Solution Through the Grace of Sant Rampal Ji Maharaj
Girawad Flood Relief Phase 2 is not merely a project. It is a new story of relief and change in the lives of farmers. All this has become possible through the grace and guidance of Sant Rampal Ji Maharaj, who, by providing pipelines, motors, and necessary materials in phases, created a path toward solving the serious problem of waterlogging.
This entire event gives the message that when a problem is solved with proper planning, dedication, and correct guidance, even a major crisis can be resolved. Now, the farmers of the village hope that in the coming time, their farming will become safer, more stable, and more beneficial.